SMS roughing mill emergency repair project

2023-03-21


SMS roughing mill emergency repair project
Case situation: Assist the customer to solve the cracking problem of the 1# rolling mill gear. The original product of the customer is imported, the procurement cycle is long, and the price is expensive.
Our company assists customers to avoid long-term downtime and cause heavy losses, and proposes to jointly develop domestically produced gear shafts to replace imported products, and control all construction periods within 2 weeks.
Transformation results: In order to solve the urgent needs of customers , our company completed the processing of the gears in just 14 days, and ensured that the precision of the gear shafts was not lower than that of imported products. After the products were installed and used, various technologies were measured The indicators fully meet the site requirements. Greatly shorten the emergency repair for customers
time, reducing the loss of orders.